Sewer Connection Check List
1. _______ Piping 4-6” PVC schedule 40 or SDR-26
2. _____ Fall no less than 1/8” and no more than 1/4”per foot
3. _____ Clean out 5’ from house and every 50’
4. _____ Clean out no less than 3” diameter
5. _____ No elbows greater than 45 degrees
6. _____ No sump pumps, down spouts, etc., hooked to system
7. _____ Rigid or rubber transition fittings w/stainless clamps at connection
8. _____ Septic pumped (receipt required)
9. _____ Septic broke and filled
10. _____ Septic outlets plugged
Address______________________________________________